Iowa Lakes Electric Cooperative (ILEC) runs two wind projects, both rated at 10.5 megawatts. Since the turbines were commissioned in 2009, the wind farms have been a positive force in the local communities by supplying clean power for neighboring ethanol production facilities and providing economic support for landowners who host wind turbines.

But running a wind farm is no easy feat.

When battery component replacement for the turbines’ emergency pitch systems became a more frequent and costly task that required additional climbs per week, ILEC approached Maxwell Technologies to integrate its ultracapacitor-based retrofit solution for greater reliability and performance in the field.

"The batteries are the root issue here," says Al Zeitz, ILEC’s manager of renewable energy services. "A lot of the challenges that we have with these battery pitch systems is that there are a lot of associated faults with the components related to the batteries."

Once ILEC installed Maxwell’s ultracapacitor-based energy storage retrofit solution in the turbines’ emergency pitch control systems, the team experienced immediate results, including:

  • Reduced number of battery-related pitch faults
  • Significant drop in number of turbine climbs necessary to address battery system failures
  • Reduced operations and maintenance costs and component replacements
  • Streamlined system performance and reliability
  • Increased turbine uptime and availability

To get a more in-depth look at how ILEC overcame battery-related issues by upgrading wind turbines with Maxwell’s ultracapacitor-based retrofit solution, download the full case study.

"Maxwell’s ultracapacitor retrofit solution and its longevity helps us toward our goal of extending the life of the wind turbines."

—Al Zeitz, manager of renewable energy services,
Iowa Lakes Electric Cooperative

Mike EverettJessica Baris
Communications Specialist and Copywriter
About this author

Jessica A. Baris is communications specialist and copywriter at Maxwell Technologies and enjoys telling a good story. Her background includes writing and editing for the high- tech, construction, and meetings and conventions industries. A San Diego native, Jessica earned a Master of Arts in rhetoric and writing from San Diego State University and a Bachelor of Arts in linguistics from the University of California, San Diego.

 

Get our blog posts delivered straight to your inbox

Opinions expressed in the content posted here are the personal opinions of the original authors, and do not necessarily reflect those of Maxwell Technologies, Inc. The content is provided for informational purposes only and is not meant to be an endorsement or representation by Maxwell or any other party. This site may also provide links or references to non-Maxwell sites and resources. Maxwell makes no representations, warranties, or other commitments whatsoever about any non-Maxwell sites or third-party resources that may be referenced, accessible from, or linked to this site.